Question No.81

Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?

  1. Burndown chart

  2. Story card

  3. Vision document

  4. Backlog

Correct Answer: D

Question No.82

In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?

  1. Release planning

  2. Sprint planning

  3. Sprint Retrospective

  4. Daily Scrum

Correct Answer: C

Question No.83

Who is responsible for prioritizing the stories that will be included in the iteration?

  1. ScrumMaster

  2. Developer

  3. Product Owner

  4. Team

Correct Answer: C

Question No.84

For a quot;caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:

  1. Whatever they choose.

  2. Individual projects.

  3. The same set of multiple projects,

  4. The same project.

Correct Answer: D

Question No.85

A project team is distributed across multiple countries, and they are having issues agreeing on what is being delivered and how it should be developed.Which of the following should the project manager do to alleviate some of the tension between team members, break down cultural barriers, and improve communication?

  1. Ask the team to communicate only through email to clearly document issues.

  2. Discuss this issue with senior management and recommend that the team be co- located.

  3. Monitor performance and discuss the issues in detail at the next retrospective.

  4. Hold daily standup meetings with the two teams at a time that works best for everyone.

Correct Answer: D

Question No.86

Acceptance tests of user stories are specified by the:

  1. Customer at the start of the iteration.

  2. Customer as late as possible during the iteration.

  3. Tester after the team has finished the coding.

  4. Development team at the start of the iteration.

Correct Answer: A

Question No.87

At a strategic level, what is the most appropriate way for an Agile team to estimate a project?

  1. Creating a strategic plan by estimating hours and days required

  2. Using an abstract measurement to estimate Product Backlog items

  3. Estimating source lines of code needed to implement the features

  4. Taking an initial set of estimates and adding an appropriate risk factor

Correct Answer: B

Question No.88

The primary purpose of a Sprint retrospective is for the team to:

  1. Review stories planned for the next sprint and provide estimates,

  2. Demonstrate completed user stories to the Product Owner.

  3. Discuss what went well, what didn#39;t, and ways to improve.

  4. Individually provide status updates on user stories in progress.

Correct Answer: C

Question No.89

Which of the following is a list of valid Agile project planning practices?

  1. Release planning, Iteration planning, and Estimation

  2. Estimation, Spike Solutions, and Iteration planning

  3. Iteration planning, Continuous Integration, and Estimation

  4. Vision, Release planning, and Performance Optimization

Correct Answer: A

Question No.90

Estimating costs for an Agile project starts with which of the following types of meetings?

  1. Project Retrospective

  2. Steering Committee

  3. Release Planning

  4. Sprint Planning

Correct Answer: C