Question No.71

The following chart lists stories for a release of an Agile project:

image

If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?

A.

3

B.

4

C.

5

D.

7

Correct Answer: B

Question No.72

When interacting with team members, the Agile project manager should:

  1. Ask team members to do things by phrasing the statement as a request rather than as a demand.

  2. Ignore team member input and emotions when important decisions have to be made.

  3. Proceed cautiously when requesting team members to do something likely to make them unhappy.

  4. Disagree with the team based on the merit of the issue without considering how the team is feeling.

Correct Answer: A

Question No.73

Which of the following statements is an accurate value statement of the Agile Manifesto?

  1. People and places over processes and guidelines

  2. Customer collaboration over contract negotiation

  3. Working software over complete specifications

  4. Managing change over managing a plan

Correct Answer: B

Question No.74

What are three processes used to begin an Agile project?

  1. Iterations, Product Road map Planning, and Number of Sprint Iterations

  2. Visioning, Product Roadmap Planning, and Product Backlog Definition

  3. Visioning, Product Backlog Definition, and Project Charter Creation

  4. Burndown chart, Product Roadmap, and sprints#39;length

Correct Answer: B

Question No.75

During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?

  1. Denoting development sequence

  2. Estimating development hours

  3. Indicating priority of a story

  4. Estimating points of a story

Correct Answer: C

Question No.76

Which of the following is an example of a visual aid used in Lean-Agile software development?

  1. Business value delivered chart

  2. Product technical specifications

  3. Automated code coverage report

  4. Scrum-of-Scrum report

Correct Answer: A

Question No.77

A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process.The project manager#39;s initial plan should be to:

  1. Institute daily standup meetings immediately.

  2. Communicate the Agile Manifesto to the team.

  3. Balance teaching principles with Agile practices.

  4. Rate the team#39;s progress in learning new methods.

Correct Answer: C

Question No.78

A technique showing Kanban work stages by comparing counted features over a time interval is called a/an:

  1. Earned value system.

  2. Fully integrated backlog.

  3. Cumulative flow diagram.

  4. Progressive elaboration.

Correct Answer: C

Question No.79

Which is the best option to improve project velocity?

  1. Shield programmers from interruptions

  2. Minimize customer involvement

  3. Shorten the iteration length

  4. Increase project team size

Correct Answer: A

Question No.80

In the Lean process, the focus is on:

  1. Managing team efficiency.

  2. Optimizing completed work across the process stream.

  3. Using the optimal resources.

  4. Cross training the team to eliminate bottlenecks.

Correct Answer: B