Question No.51

Robert#39;s program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

  1. Lead time

  2. Crashing

  3. Lag time

  4. Fast tracking

Correct Answer: B

Question No.52

Which of the following statements is the most accurate when it comes to program change requests for the program scope?

  1. The change request must not affect the schedule.

  2. The change request must not affect the overall cost.

  3. The quality of the program must not be affected by the change request.

  4. The change request must be documented.

Correct Answer: D

Question No.53

You are identifying stakeholders for your program to create new software for your organization. The software will affect the ordering by the customer, the manufacturing of the product, inventory, and account management. Sarah, a key stakeholder in your program, is skeptical of one application affecting so many parts of the organization. She prefers that several applications be created instead of the approach your program will take. In stakeholder identification how would you categorize Sarah?

  1. Active

  2. Negative

  3. PositiveD. Passive

Correct Answer: B

Question No.54

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

  1. Summarize the project variance.

  2. Archive the project records.

  3. Summarize the project risks costs.

  4. Close the project office.

Correct Answer: B

Question No.55

Which of the following statements is most accurate about the critical path?

  1. The critical path is always one path that shows the project duration.

  2. The critical path has no float.

  3. The critical path is the longest path because it has the most activities.

  4. The critical path reveals which path has the most risk of failure.

    Correct Answer: B

    Question No.56

    You are the program manager for the BHN Program. Your program has 122 stakeholders that you#39;ll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?

    A.

    244

    B.

    122

    C.

    14,884

    D.

    7,381

    Correct Answer: D

    Question No.57

    You are the program manager of the HNG Program. This program has a budget at completion of

    $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you#39;re slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

    A.

    -$85,230

    B.

    $821,065

    C.

    -$284,100

    D.

    -$117,295

    Correct Answer: D

    Question No.58

    Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

    1. Program architecture baseline

    2. Program risk register

    3. Program WBS

    4. Program charter

Correct Answer: D

Question No.59

In which of the following processes is the program charter created?

  1. Establish Program Financial Framework

  2. Plan Program Scope

  3. Initiate Program

  4. Develop Program Management Plan

Correct Answer: C

Question No.60

You are the program manager of the HNG Program. This program has a budget at completion of

$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you#39;re slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

  1. 17

  2. 11

  3. 15

  4. 14

Correct Answer: B