[Free] 2019(Nov) EnsurePass PMI PgMP Dumps with VCE and PDF 301-310

Get Full Version of the Exam
http://www.EnsurePass.com/PgMP.html

Question No.301

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

  1. Fast tracking

  2. Compressing

  3. Float

  4. Crashing

Correct Answer: A

Question No.302

As a Program Manager, you decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

  1. Storming

  2. Forming

  3. Team development

  4. Cost of quality

Correct Answer: C

Question No.303

Which of the following individual should respond to the risk with the preplanned risk response?

  1. Key stakeholder

  2. Project manager

  3. Risk owner

  4. Project sponsor

Correct Answer: C

Question No.304

Which of the following contract types is described in the statement below?

quot;The seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed payment calculated as a percentage for the initial estimated project costs.quot;

  1. Cost Plus Fixed Fee Contracts (CPFF)

  2. Cost Plus Incentive Fee Contracts (CPIF)

  3. Fixed Price Incentive Fee Contracts (FPIF)

  4. Firm Fixed Price Contracts (FFP)

Correct Answer: A

Question No.305

Who owns the program?

  1. Project manager

  2. Program director

  3. Program sponsor

  4. Program manager

Correct Answer: B

Question No.306

Which of the following information gathering techniques is described in the statement below?

quot;Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment.quot;

  1. Brainstorming

  2. SWOT analysis

  3. Checklist analysis

  4. Delphi technique

Correct Answer: D

Question No.307

Which project management meeting allows stakeholders to meet one another and to learn about the project?

  1. Project kick-off meeting

  2. Project authorization meeting

  3. Project status meeting

  4. Project scope review

Correct Answer: A

Question No.308

According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

  1. 7

  2. 11

  3. 9

  4. 5

Correct Answer: C

Question No.309

Which of the following risk identification techniques is described in the statement below?

quot;It is used to gather information where participants don#39;t know each other nor do they have to be present at the same location.quot;

  1. Brainstorming

  2. Delphi

  3. SWOT analysis

  4. Assumptions analysis

Correct Answer: B

Question No.310

An organization supports both programs and projects for various industries. What is a portfolio?

  1. A portfolio describes the organization of related projects, programs, and operations.

  2. A portfolio is the total amount of funds that have been invested in programs, projects,and operations.

  3. A portfolio describes all of the monies that are invested in the organization.

  4. A portfolio describes any project or program within one industry or application areA.

Correct Answer: A

Get Full Version of the Exam
PgMP Dumps
PgMP VCE and PDF

Leave a Reply

Your email address will not be published. Required fields are marked *

Proudly powered by WordPress